06/05/08 Update

 

Info from the EAA meeting 6/4/08. From Mike J. via Mark Harrington:
The contractor is Columbine Concrete.
The contract will be signed 6/24
Work will start on 6/25 ( do not know when the airport will be closed)
The BOCC has approved 500' additional runway complete this year.
(Do not know the total length to be completed this year)
A letter will be sent to hangar owners with additional schedule information.

 

Also:
Updated information on tie downs at Kremmling from Brett, Airport Operations and Maintenance Manager.
20 tie downs will be made available for GNB aircraft at no charge.
9 are on the asphalt on a first come basis.
11 are on the gravel - Brett will be installing tie downs in the gravel area.